Waterview tunnel halfway there

6:14 am on 30 September 2014

It will now be several months before the world's largest operating tunnel boring machine is turned around and started again after it emerged deep from underground.

The machine, known as 'Alice', is now halfway through its task of building the Waterview motorway connection in Auckland. It took 10 months before it broke through - it started in the suburb of Owairaka 2.4km away.

Watch more here:

The New Zealand Transport Agency says the tunnel which Alice has made has the 10th biggest diameter in the world, and it is also the country's longest road tunnel.

But it has another identical tunnel to make by heading in the other direction.

The drill's cutting head and three trailing gantries will be disconnected and, one piece at a time, taken from the completed tunnel and turned around. The parts will not be reconnected until early next year.

The tunnel boring machine is 90 metres long and weighs in at 3100 tonnes and its cutting head and shield are as high as a four storey building.

Project manager John Burden says the rotation will be "a big deal". "She gets pushed out of the ground onto a special cable that then gets dragged around by some large jacks ... it is a big job to pull her around and position her accurately."

Peter Spies from the New Zealand Transport Agency.

Peter Spies from the New Zealand Transport Agency. Photo: RNZ / Kim Baker Wilson

A New Zealand Transport Agency spokesman, Peter Spies, said Monday's breakthrough was a fantastic achievement.

"You stand looking in anticipation at a solid concrete wall expecting the machine to come through exactly where the surveyors said it would come through. And although you have trust in your surveyors, when you see it come through exactly where planned it's an absolutely brilliant feeling."

The completed tunnel and the one yet to be built form a $1.4 billion project. It will be a six-lane motorway linking the existing South-Western and North-Western motorways to help form the Western Ring Route. Vehicles will travel at up to 40 metres below the surface.

The project is scheduled to finish in 2017 because there will still be a year of work to fit the tunnels out after the second one is drilled.

The Waterview Connection is prioritised by the Government as one of its Roads of National Significance.

What's next

  • Disconnect Alice's cutting head and three trailing gantries and turn them around
  • Turn around the machine's conveyor system that has been removing excavated material
  • Turn around a fourth gantry which installs a culvert on the tunnel floor
  • Start and complete drilling the second tunnel
  • Complete a year's worth of work fitting out both tunnels with ventilation buildings and cross passages
  • Finish new cycleways and walkways, playgrounds and skateparks, and plant 150,000 trees and shrubs