An agreement to pay standardised compensation for disruption during a lines upgrade project in the lower South Island has been hailed as a major step forward by a landowners group.

The $170 million project to add more lines on existing towers and replace and strengthen some towers between the Clutha and Waitaki rivers is expected to be completed by 2016.

Transpower chief executive Patrick Strange says compensation will be based on the number of towers on each property, and about $2 million will be paid out.

The Roxburgh to Duntroon landowners group says the agreement is a breakthrough after recent deadlock between Transpower and landowners in Auckland and South Canterbury.

However South Canterbury farmer Jeremy Talbot, who has been battling Transpower for annual pylon payments for years, says the deal is just a goodwill gesture, as under the Public Works Act the company is required to pay for any damage .

Mr Talbot says landowners want Transpower to treat them the same as new line hosts.

Listen to item on Morning Report


Radio New Zealand Audio

hide window

Audio is categorised based on the frequency of the programme it was heard in. Click on the headings below to access the programmes. If you are unsure where to look, try the latest audio page.

Live Audio Streams

Streams are in Windows Media format. Mac and Linux users see our help section.

If you use Windows Vista and streaming has stopped working see our help section.

National Daily On Demand

National Weekly Audio On Demand

Concert On Demand

Music On Demand

Documentaries, Lectures and Forums

Parliament Audio

Podcasts & Downloads

Downloads and Podcasts are available on selected programmes. Our podcast page has a complete list of feeds.

Audio Help

Access Key List

Why does this site look so plain?